Accrued and estimated investment costs. Extraction of crude petroleum and natural gas and transport via pipelines. 2010-2015. Million NOK
 201020112012201320141201422015120152
1Registered 2nd quarter 2014.
2Registered 1st quarter 2014.
3Includes offices, bases and terminals onshore.
Total127 290147 679173 482211 883227 267231 700185 256182 420
         
Total extraction of crude petroleum and natural gas126 738147 210173 145208 638222 355225 113180 410177 516
         
Exploration and concept studies25 49327 39926 99033 90435 11335 66532 21833 331
         
Field development and Fields on stream92 587112 987141 009168 321173 952176 916133 647131 779
         
Field development30 35237 47551 98463 22577 29183 56854 97856 331
Commodities12 47521 16124 36727 46336 61539 11428 50426 749
Services7 1878 07715 94123 10121 98223 0159 69711 036
Production drilling10 6908 23711 67612 66118 69421 43916 77718 545
         
Fields on stream62 23575 51389 024105 09696 66193 34878 66975 448
Commodities4 7975 2948 6029 29011 0289 4788 6806 860
Services24 27330 92836 55239 84935 37335 46523 23323 993
Production drilling33 16539 29143 87055 95750 26048 40546 75644 595
         
Onshore activities36 7885 4344 1303 6095 1765 1244 5354 549
         
Shutdown and removal1 8691 3901 0172 8048 1147 40810 0117 857
         
Transport via pipelines5524693373 2454 9126 5874 8464 905