Change in per cent | September 2014 | Weight pr cent1 | ||
---|---|---|---|---|
August 2014 - September 2014 | September 2013 - September 2014 | |||
1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded. | ||||
Plumbing costs total | 0.1 | 2.1 | 191.9 | 100,0 |
Administrative expenses | 0.0 | 2.4 | 163.1 | 17,3 |
Labour costs | 0.0 | 2.0 | 173.1 | 26,0 |
Materials | 0.0 | 2.1 | 209.5 | 55,3 |
Sanitary installations | 0.0 | 0.8 | 191.1 | 54,5 |
Materials | 0.0 | 0.0 | 205.0 | 32,7 |
Heating installations | 0.0 | 3.8 | 192.9 | 45,5 |
Materials | 0.0 | 5.1 | 215.8 | 22,6 |