Total127 290147 679173 482211 883218 584227 267188 570185 256
         
Total extraction of crude petroleum and natural gas126 738147 210173 145208 638213 909222 355183 718180 410
         
Exploration and concept studies25 49327 39926 99033 90435 14335 11331 69932 218
         
Field development and Fields on stream92 587112 987141 009168 321165 638173 952136 158133 647
         
Field development30 35237 47551 98463 22573 86577 29157 61454 978
Commodities12 47521 16124 36727 46333 46736 61528 08828 504
Services7 1878 07715 94123 10121 48221 98211 0939 697
Production drilling10 6908 23711 67612 66118 91618 69418 43316 777
         
Fields on stream62 23575 51389 024105 09691 77296 66178 54478 669
Commodities4 7975 2948 6029 2909 25111 0288 2168 680
Services24 27330 92836 55239 84934 17735 37323 43723 233
Production drilling33 16539 29143 87055 95748 34550 26046 89146 756
         
Onshore activities36 7885 4344 1303 6094 6845 1764 1854 535
         
Shutdown and removal1 8691 3901 0172 8048 4448 11411 67610 011
         
Transport via pipelines5524693373 2454 6754 9124 8524 846