Change in per cent | December 2014 | Weight pr cent1 | ||
---|---|---|---|---|
November 2014 - December 2014 | December 2013 - December 2014 | |||
1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded. | ||||
Plumbing costs total | 0.0 | 1.9 | 192.8 | 100,0 |
Administrative expenses | 0.0 | 2.5 | 164.5 | 17,3 |
Labour costs | 0.0 | 3.4 | 176.0 | 26,0 |
Materials | 0.0 | 1.2 | 209.5 | 55,3 |
Sanitary installations | 0.0 | 0.7 | 191.9 | 54,5 |
Materials | 0.0 | -0.5 | 205.0 | 32,7 |
Heating installations | 0.0 | 3.4 | 194.0 | 45,5 |
Materials | 0.0 | 3.7 | 215.8 | 22,6 |