Change in per cent | September 2015 | Weight pr cent1 | ||
---|---|---|---|---|
August 2015 - September 2015 | September 2014 - September 2015 | |||
1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded. | ||||
Plumbing costs total | -0.1 | 2.4 | 196.5 | 100,0 |
Administrative expenses | -0.1 | 1.8 | 166.1 | 17,3 |
Labour costs | 0.0 | 3.1 | 178.4 | 26,0 |
Materials | 0.0 | 2.4 | 214.5 | 55,3 |
Sanitary installations | 0.0 | 2.9 | 196.6 | 54,5 |
Materials | 0.0 | 3.1 | 211.4 | 32,7 |
Heating installations | -0.1 | 1.9 | 196.5 | 45,5 |
Materials | 0.0 | 1.4 | 218.9 | 22,6 |