Construction cost index for plumbing works in office and commercial buildings. 2000=100
Change in per centSeptember 2015Weight pr cent1
August 2015 - September 2015September 2014 - September 2015
1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded.
Plumbing costs total-0.12.4196.5100,0
Administrative expenses-0.11.8166.117,3
Labour costs0.03.1178.426,0
Materials0.02.4214.555,3
 
Sanitary installations0.02.9196.654,5
Materials0.03.1211.432,7
 
Heating installations-0.11.9196.545,5
Materials0.01.4218.922,6