Table

Construction cost index for plumbing works in office and commercial buildings. 2000=100
May 2017May 2018Change from previous year (per cent)Weight pr cent
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively
Plumbing costs total207.8214.83.4100,0
Administrative expenses174.2179.43.017,3
Labour costs1186.4191.93.026,0
Materials228.2236.53.655,3
 
Sanitary installations206.0212.13.054,5
Administrative expenses174.2179.43.08,4
Labour cost1186.4191.93.012,4
Materials221.7228.33.032,7
 
Heating installations210.0218.03.845,5
Administrative expenses174.2179.43.08,9
Labour cost1186.4191.93.013,4
Materials237.6248.14.422,6