August 2018 | August 2019 | Change from previous year (per cent) | Weight pr cent | |
---|---|---|---|---|
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively | ||||
Plumbing costs total | 214.9 | 221.4 | 3.0 | 100,0 |
Administrative expenses | 181.7 | 184.3 | 1.4 | 17,3 |
Labour costs1 | 193.6 | 197.1 | 1.8 | 26,0 |
Materials | 235.1 | 244.2 | 3.9 | 55,3 |
Sanitary installations | 213.8 | 218.4 | 2.2 | 54,5 |
Administrative expenses | 181.7 | 184.3 | 1.4 | 8,4 |
Labour cost1 | 193.6 | 197.1 | 1.8 | 12,4 |
Materials | 229.9 | 235.3 | 2.3 | 32,7 |
Heating installations | 216.3 | 225.0 | 4.0 | 45,5 |
Administrative expenses | 181.7 | 184.3 | 1.4 | 8,9 |
Labour cost1 | 193.6 | 197.1 | 1.8 | 13,4 |
Materials | 242.8 | 257.0 | 5.8 | 22,6 |