Table

Construction cost index for plumbing works in office and commercial buildings. 2000=100
December 2018December 2019Change from previous year (per cent)Weight pr cent
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively
Plumbing costs total214.7221.53.2100,0
Administrative expenses182.7184.10.817,3
Labour costs1192.2197.52.826,0
Materials235.1244.23.955,3
 
Sanitary installations213.6218.52.354,5
Administrative expenses182.7184.10.88,4
Labour cost1192.2197.52.812,4
Materials229.9235.32.332,7
 
Heating installations216.1225.24.245,5
Administrative expenses182.7184.10.88,9
Labour cost1192.2197.52.813,4
Materials242.8257.05.822,6