January 2019 | January 2020 | Change from previous year (per cent) | Weight pr cent | |
---|---|---|---|---|
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively | ||||
Plumbing costs total | 217.6 | 227.0 | 4.3 | 100,0 |
Administrative expenses | 179.7 | 184.1 | 2.4 | 17,3 |
Labour costs1 | 192.2 | 197.5 | 2.8 | 26,0 |
Materials | 241.2 | 253.8 | 5.2 | 55,3 |
Sanitary installations | 215.4 | 224.2 | 4.1 | 54,5 |
Administrative expenses | 179.7 | 184.1 | 2.4 | 8,4 |
Labour cost1 | 192.2 | 197.5 | 2.8 | 12,4 |
Materials | 233.4 | 244.6 | 4.8 | 32,7 |
Heating installations | 220.4 | 230.3 | 4.5 | 45,5 |
Administrative expenses | 179.7 | 184.1 | 2.4 | 8,9 |
Labour cost1 | 192.2 | 197.5 | 2.8 | 13,4 |
Materials | 252.5 | 267.1 | 5.8 | 22,6 |