October 2019 | October 2020 | Change from previous year (per cent) | Weight pr cent | |
---|---|---|---|---|
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively | ||||
Plumbing costs total | 221.4 | 233.1 | 5.3 | 100,0 |
Administrative expenses | 184.1 | 186.3 | 1.0 | 17,3 |
Labour costs1 | 197.1 | 200.8 | 1.9 | 26,0 |
Materials | 244.2 | 262.7 | 7.6 | 55,3 |
Sanitary installations | 218.4 | 231.6 | 6.0 | 54,5 |
Administrative expenses | 184.1 | 186.3 | 1.0 | 8,4 |
Labour cost1 | 197.1 | 200.8 | 1.9 | 12,4 |
Materials | 235.3 | 255.2 | 8.5 | 32,7 |
Heating installations | 225.1 | 235.0 | 4.4 | 45,5 |
Administrative expenses | 184.1 | 186.3 | 1.0 | 8,9 |
Labour cost1 | 197.1 | 200.8 | 1.9 | 13,4 |
Materials | 257.0 | 273.7 | 6.5 | 22,6 |