Table

Construction cost index for plumbing works in office and commercial buildings. 2000=100
January 2020January 2021Change from previous year (per cent)Weight pr cent
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively
Plumbing costs total227.0235.53.7100,0
Administrative expenses184.1187.51.817,3
Labour costs1197.5200.51.526,0
Materials253.8266.75.155,3
 
Sanitary installations224.2234.14.454,5
Administrative expenses184.1187.51.88,4
Labour cost1197.5200.51.512,4
Materials244.6258.95.832,7
 
Heating installations230.3237.33.045,5
Administrative expenses184.1187.51.88,9
Labour cost1197.5200.51.513,4
Materials267.1277.84.022,6