Construction cost index, civil engineering works

2   Construction cost index for maintenance of road and provincial road. 1st Quarter 1985=100
  Weight 2000 2001 2002 Per cent
  2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 2nd Quarter 01-2nd Quarter 02 1st Quarter 02-2nd Quarter 02
Total 1 000.0  180.6  182.6  186.8  187.8  186.8  187.7  189.1  188.3  190.6 2.0 1.2
Materials  299.7  169.9  171.1  172.2  174.1  174.8  175.8  176.4  178.2  179.9 2.9 1.0
Machinery  522.0  188.7  190.8  196.9  197.1  194.2  194.6  195.4  193.3  196.2 1.0 1.5
Labour costs  178.4  183.3  186.7  191.1  193.7  194.8  196.7  201.1  200.3  201.5 3.4 0.6
                         
The road,bridges and quays, total  253.0  183.0  185.0  188.6  190.0  189.2  190.0  191.2  190.7  192.9 1.9 1.1
Materials  105.7  174.0  175.4  176.5  178.8  179.4  180.1  180.7  182.3  183.9 2.5 0.9
                         
Road surfaces, total  206.7  175.1  176.9  181.0  182.2  181.1  182.4  183.5  183.3  185.4 2.4 1.1
Materials 72.3  164.4  165.5  167.1  169.4  169.9  172.2  172.2  175.0  176.5 3.9 0.8
                         
Signs, marking, clearing and cleaning, total  254.7  179.2  181.0  184.5  185.6  185.4  186.2  187.9  187.6  189.6 2.2 1.0
Materials  106.0  168.6  169.6  170.5  171.5  172.5  173.0  174.0  175.2  176.9 2.6 1.0
                         
Maintenance in wintertime, total  284.8  186.3  188.5  194.0  194.6  192.6  193.2  194.6  192.9  195.4 1.4 1.3
Materials 15.4  156.6  158.2  159.6  161.4  161.9  162.8  163.2  165.4  167.4 3.4 1.2
                         
Avalanches, flods etc., total 0.8  185.1  187.1  191.2  192.3  191.5  192.6  194.1  193.2  195.7 2.2 1.3
Materials 0.2  172.7  173.5  174.1  175.5  176.9  178.9  179.6  181.2  183.4 3.7 1.2

Explanation of symbols