Building and construction, order statistics

4   Stock of orders by duration, project groups and district. 3. quarter 2001. Per cent
  Total Buildings Civil engineering works
  Accomplished in 12 months Accomplished after 12 months Accomplished in 12 months Accomplished after 12 months Accomplished in 12 months Accomplished after 12 months
Total 83 17 85 15 74 26
Oslo, Akershus og Østfold 81 19 82 18 75 25
Hedmark og Oppland 94 6 97 3 76 24
Telemark, Vestfold og Buskerud 89 11 91 9 80 20
Aust-Agder og Vest-Agder 80 20 87 13 61 39
Rogaland 91 9 94 6 82 18
Hordaland og Sogn og Fjordane 82 18 90 10 68 32
Møre og Romsdal, Sør-Trøndelag og Nord-Trøndelag 79 21 81 19 64 36
Nordland, Troms og Finnmark 83 17 83 17 83 17