Higher costs for road construction
The construction costs for main roads and provincial roads rose by 2.8 per cent from the 3rd quarter to the 4th quarter 2003. The labour costs increased by 4.5 per cent during this period.
The machinery and the material costs rose by 3.8 and 1.3 per cent respectively in the same period. The cost for mass moving increased the most, by 3.7 per cent at the same time. The price increase of diesel is the main reason for the increasing costs of the machinery.
From the 3rd to the 4th quarter of 2003, the construction costs for main roads and provincial roads increased by 0.8 per cent. The labour costs, the material costs and the machinery costs rose by 2.5, 0.7 and 0.1 per cent respectively in the same period.
Maintenance of roads
The construction costs for maintenance of main roads and provincial roads increased by 0.9 per cent from the 3rd to the 4th quarter 2003 and is 3.9 per cent higher than a year before.
Construction cost index for civil engineering works. 1st Quarter 1985=100 |
4th Quarter 2003 | Change in per cent | ||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
3rd Quarter 2003-
4th Quarter 2003 |
4th Quarter 2002-
4th Quarter 2003 |
||||||||||||||||||||||||||||||||||||||
Main road and provincial road | |||||||||||||||||||||||||||||||||||||||
Total | 200.6 | 0.8 | 2.8 | ||||||||||||||||||||||||||||||||||||
Materials | 184.2 | 0.1 | 1.3 | ||||||||||||||||||||||||||||||||||||
Machinery | 207.6 | 0.7 | 3.8 | ||||||||||||||||||||||||||||||||||||
Labour cost | 220.6 | 2.5 | 4.5 | ||||||||||||||||||||||||||||||||||||
Maintenance of road and provincial road | |||||||||||||||||||||||||||||||||||||||
Total | 200.7 | 0.9 | 3.3 | ||||||||||||||||||||||||||||||||||||
Materials | 183.2 | 0.2 | 1.7 | ||||||||||||||||||||||||||||||||||||
Machinery | 207.6 | 0.7 | 3.8 | ||||||||||||||||||||||||||||||||||||
Labour cost | 220.6 | 2.5 | 4.5 | ||||||||||||||||||||||||||||||||||||
Water power plant | |||||||||||||||||||||||||||||||||||||||
Total | 195.4 | 1.0 | 2.4 | ||||||||||||||||||||||||||||||||||||
Materials | 181.1 | -0.2 | 0.8 | ||||||||||||||||||||||||||||||||||||
Tables:
Additional information
Contact
-
Martin Handeland Skjæveland
E-mail: martin.skjaeveland@ssb.no
tel.: (+47) 40 81 14 17
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28