Small changes in plumbing costs
The index of plumbing works in office and commercial buildings increased by 0.1 per cent in January 2004 compared with December 2003.
In the same period the cost of sanitary installations rose by 0.1 per cent, while heating installations remained unchanged.
The construction costs of plumbing works in office and commercial buildings rose by 4.9 per cent in January 2004 compared with January 2003. In the same period the costs of sanitary installations and heating installations rose by 4.7 and 5.3 per cent respectively.
Construction cost index for plumbing works in
office and commercial buildings. 2000=100 |
Weigth
per cent1 |
Change in per cent | ||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
January 2004 |
December 2003-
January 2004 |
January 2003-
January 2004 |
|||||||||||||||||||||||||||||||||||||
Plumbing costs total | 100.0 | 120.3 | 0.1 | 4.9 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 115.3 | 0.1 | 2.4 | |||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 122.2 | 0.2 | 6.8 | |||||||||||||||||||||||||||||||||||
Materials | 55.3 | 121.1 | 0.0 | 4.8 | |||||||||||||||||||||||||||||||||||
Sanitary installastions | 54.5 | 120.6 | 0.1 | 4.7 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 8.4 | 115.3 | 0.1 | 2.4 | |||||||||||||||||||||||||||||||||||
Labour costs | 12.6 | 122.2 | 0.2 | 6.8 | |||||||||||||||||||||||||||||||||||
Materials | 32.7 | 121.4 | 0.0 | 4.3 | |||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 119.9 | 0.0 | 5.3 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 8.9 | 115.3 | 0.1 | 2.4 | |||||||||||||||||||||||||||||||||||
Labour costs | 13.4 | 122.2 | 0.2 | 6.8 | |||||||||||||||||||||||||||||||||||
Materials | 22.6 | 120.6 | 0.0 | 5.5 | |||||||||||||||||||||||||||||||||||
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12