Plumbing costs up 6.7 per cent
The index of plumbing works in office and commercial buildings shows an increase in plumbing costs of 6.7 per cent from July last year to July this year. In the same period, material costs rose by 9.1 per cent.
The construction costs of plumbing works in office and commercial buildings increased by 0.2 per cent from June to July this year. The material costs rose by 0.5 per cent in the same period.
Construction cost index for plumbing works in
office and commercial buildings. 2000=100 |
Weigth per cent1 | July 2004 | Change in per cent | |||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
June-July
2004 |
July 2003-
July 2004 |
||||||||||||||||||||||||||||||||||||||
Plumbing costs total | 100.0 | 125.1 | 0.2 | 6.7 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 115.9 | 0.0 | 2.5 | |||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 122.8 | 0.0 | 4.5 | |||||||||||||||||||||||||||||||||||
Materials | 55.3 | 129.3 | 0.5 | 9.1 | |||||||||||||||||||||||||||||||||||
Sanitary installastions | 54.5 | 125.0 | 0.0 | 5.9 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 8.4 | 115.9 | 0.0 | 2.5 | |||||||||||||||||||||||||||||||||||
Labour costs | 12.6 | 122.8 | 0.0 | 4.5 | |||||||||||||||||||||||||||||||||||
Materials | 32.7 | 128.4 | 0.0 | 7.4 | |||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 125.3 | 0.6 | 7.7 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 8.9 | 115.9 | 0.0 | 2.5 | |||||||||||||||||||||||||||||||||||
Labour costs | 13.4 | 122.8 | 0.0 | 4.5 | |||||||||||||||||||||||||||||||||||
Materials | 22.6 | 130.7 | 1.2 | 11.6 | |||||||||||||||||||||||||||||||||||
1 |
The sum of weights for administrative expenses, labour costs and
materials deviate from 100 because transport costs are excluded. |
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings