Stable plumbing costs
The index of plumbing works in office and commercial buildings rose by 0.1 per cent from March to April this year. The material costs remained unchanged in the same period.
In the period April 2005 to April 2006 the construction costs of plumbing works in office and commercial buildings increased by 2.9 per cent. The costs of sanitary installations and heating installations rose by 4.3 and 1.4 per cent respectively in the same period.
Construction cost index for plumbing works in office and
commercial buildings. 2000=100 |
Weigth per cent1 | April 2006 | Change in per cent | |||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
March 2006-
April 2006 |
April 2005-
April 2006 |
||||||||||||||||||||||||||||||||||||||
Plumbing costs, total | 100.0 | 134.0 | 0.1 | 2.9 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 122.6 | 0.1 | 3.6 | |||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 129.5 | 0.0 | 2.4 | |||||||||||||||||||||||||||||||||||
Materials | 55.3 | 139.7 | 0.0 | 2.9 | |||||||||||||||||||||||||||||||||||
Sanitary installations | 54.5 | 134.8 | 0.1 | 4.3 | |||||||||||||||||||||||||||||||||||
Materials | 32.7 | 140.0 | 0.0 | 5.1 | |||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 133.1 | 0.1 | 1.4 | |||||||||||||||||||||||||||||||||||
Materials | 22.6 | 139.4 | 0.0 | 0.1 | |||||||||||||||||||||||||||||||||||
1 |
The sum of weights for administrative expenses, labour costs and materials
deviate from 100 because transport costs are excluded. |
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings