Stable plumbing costs
The index of plumbing works in office and commercial buildings remained unchanged in July compared with June 2007.
The construction costs of plumbing works in office and commercial buildings increased by 7.9 per cent from July 2006 to July 2007.
Construction cost index for plumbing works in office and commercial
buildings. 2000=100 |
Weigth per cent1 | July2007 | Change in per cent | |||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
June 2007-July 2007 | July 2006-July 2007 | ||||||||||||||||||||||||||||||||||||||
Plumbing costs total | 100.0 | 147.1 | 0.0 | 7.9 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 128.0 | 0.0 | 3.6 | |||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 138.0 | 0.0 | 6.4 | |||||||||||||||||||||||||||||||||||
Materials | 55.3 | 157.4 | 0.0 | 9.7 | |||||||||||||||||||||||||||||||||||
Sanitary installastions | 54.5 | 147.9 | 0.0 | 6.9 | |||||||||||||||||||||||||||||||||||
Materials | 32.7 | 156.8 | 0.0 | 7.8 | |||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 146.2 | 0.0 | 9.1 | |||||||||||||||||||||||||||||||||||
Materials | 22.6 | 158.1 | 0.0 | 12.4 | |||||||||||||||||||||||||||||||||||
1 |
The sum of weights for administrative expenses, labour costs and materials deviate from 100
because transport costs are excluded. |
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12