Plumbing costs up 5.2 per cent
From December 2006 to December 2007, the construction costs of plumbing works in office and commercial buildings rose by 5.2 per cent. From November to December, the costs increased by 0.2 per cent.
The costs of sanitary installations and heating installations rose by 3.7 and 6.8 per cent respectively from December 2006 to December 2007.
Weigth per cent1 | December 2007 | Change in per cent | |||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
November 2007-
December 2007 |
December 2006-
December 2007 |
||||||||||||||||||||||||||||||||||||||
Plumbing costs total | 100.0 | 149.1 | 0.2 | 5.2 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 132.2 | 0.8 | 3.5 | |||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 143.7 | 0.0 | 5.4 | |||||||||||||||||||||||||||||||||||
Materials | 55.3 | 156.9 | 0.0 | 5.4 | |||||||||||||||||||||||||||||||||||
Sanitary installastions | 54.5 | 148.1 | 0.1 | 3.7 | |||||||||||||||||||||||||||||||||||
Materials | 32.7 | 154.0 | 0.0 | 3.1 | |||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 150.2 | 0.1 | 6.8 | |||||||||||||||||||||||||||||||||||
Materials | 22.6 | 161.1 | 0.0 | 8.7 | |||||||||||||||||||||||||||||||||||
1 |
The sum of weights for administrative expenses, labour costs and materials deviate from
100 because transport costs are excluded. |
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12