Plumbing costs unchanged
The construction costs of plumbing works in office and commercial buildings remained unchanged from June to July this year.
The construction costs of plumbing works in office and commercial buildings rose by 4.0 per cent from July 2008 to July 2009. The costs of sanitary installations and heating installations increased by 3.1 and 5.2 per cent respectively in the same period.
Weigth per cent1 | July 2009 | Change in per cent | |||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
June 2009-
July 2009 |
July 2008-
July 2009 |
||||||||||||||||||||||||||||||||||||||
Plumbing costs total | 100.0 | 164.1 | 0.0 | 4.0 | |||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 139.9 | 0.3 | 4.5 | |||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 146.9 | 0.0 | 1.3 | |||||||||||||||||||||||||||||||||||
Materials | 55.3 | 179.6 | 0.0 | 5.0 | |||||||||||||||||||||||||||||||||||
Sanitary installastions | 54.5 | 161.0 | 0.1 | 3.1 | |||||||||||||||||||||||||||||||||||
Materials | 32.7 | 171.7 | 0.0 | 3.3 | |||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 167.9 | 0.0 | 5.2 | |||||||||||||||||||||||||||||||||||
Materials | 22.6 | 190.9 | -0.1 | 7.3 | |||||||||||||||||||||||||||||||||||
1 |
The sum of weights for administrative expenses, labour costs and materials
deviate from 100 because transport costs are excluded. |
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12