Content
Published:
This is an archived release.
Plumbing costs unchanged
From November to December 2012, the construction costs of plumbing works in office and commercial buildings remained unchanged.
The construction costs of plumbing works in office and commercial buildings rose by 3.1 per cent from December 2011 to December 2012. The material costs increased by 3.5 per cent in the same period.
The costs of sanitary installations and heating installations rose by 3.3 and 2.8 per cent respectively, while the material costs increased by 3.7 and 3.1 per cent in the same period.
Weigth
per cent1 |
December 2012 | Change in per cent | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
November 2012-
December 2012 |
December 2011-
December 2012 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Plumbing costs total | 100.0 | 185.8 | 0.0 | 3.1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Administrative expenses | 17.3 | 155.4 | 0.1 | 2.9 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Labour costs | 26.0 | 164.6 | 0.0 | 2.2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Materials | 55.3 | 205.0 | 0.0 | 3.5 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sanitary installastions | 54.5 | 186.8 | 0.0 | 3.3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Materials | 32.7 | 203.3 | 0.0 | 3.7 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Heating installations | 45.5 | 184.5 | 0.1 | 2.8 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Materials | 22.6 | 207.2 | 0.0 | 3.1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 |
The sum of weights for administrative expenses, labour costs and materials deviate from 100
because transport costs are excluded. |
Tables:
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12