Stable plumbing costs
The construction costs of plumbing works in office and commercial buildings rose by 0.1 per cent from December 2012 to January 2013. The material costs remained unchanged in the same period.
Change in per cent | January 2013 | Weight pr cent1 | ||
---|---|---|---|---|
December 2012 - January 2013 | January 2012 - January 2013 | |||
1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded. | ||||
Plumbing costs total | 0.1 | 2.3 | 185.9 | 100,0 |
Administrative expenses | 0.4 | 3.2 | 156.0 | 17,3 |
Labour costs | 0.0 | 2.2 | 164.6 | 26,0 |
Materials | 0.0 | 2.1 | 204.9 | 55,3 |
Sanitary installations | 0.5 | 2.9 | 187.8 | 54,5 |
Materials | 0.7 | 3.0 | 204.7 | 32,7 |
Heating installations | -0.4 | 1.7 | 183.7 | 45,5 |
Materials | -0.9 | 0.9 | 205.3 | 22,6 |
From December 2012 to January 2013, the costs of sanitary installations increased by 0.5 per cent, while the costs of heating installations decreased by 0.4 per cent.
From January last year to January this year, the construction costs of plumbing works in office and commercial buildings rose by 2.3 per cent.
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12