Plumbing costs unchanged
The construction costs of plumbing works in office and commercial buildings remained unchanged from March to April this year, and are 2.0 per cent higher than in April 2012.
Change in per cent | April 2013 | Weight pr cent1 | ||
---|---|---|---|---|
March 2013 - April 2013 | April 2012 - April 2013 | |||
1The sum of weights for administrative expenses, labour costs and materials deviate from 100 because transport costs are excluded. | ||||
Plumbing costs total | 0.0 | 2.0 | 186.1 | 100,0 |
Administrative expenses | 0.1 | 3.4 | 157.1 | 17,3 |
Labour costs | 0.0 | 2.1 | 164.9 | 26,0 |
Materials | 0.0 | 1.8 | 204.9 | 55,3 |
Sanitary installations | 0.0 | 2.6 | 187.9 | 54,5 |
Materials | 0.0 | 2.8 | 204.7 | 32,7 |
Heating installations | 0.0 | 1.4 | 184.0 | 45,5 |
Materials | 0.0 | 0.5 | 205.3 | 22,6 |
From April 2012 to April 2013, the costs of sanitary installations and heating installations rose by 2.6 and 1.4 per cent respectively.
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings