Content
Published:
This is an archived release.
June 2017 | June 2018 | Change from previous year (per cent) | Weight pr cent | |
---|---|---|---|---|
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively | ||||
Plumbing costs total | 207.8 | 214.8 | 3.4 | 100,0 |
Administrative expenses | 174.0 | 179.3 | 3.0 | 17,3 |
Labour costs1 | 186.4 | 191.9 | 3.0 | 26,0 |
Materials | 228.2 | 236.5 | 3.6 | 55,3 |
Sanitary installations | 205.9 | 212.1 | 3.0 | 54,5 |
Administrative expenses | 174.0 | 179.3 | 3.0 | 8,4 |
Labour cost1 | 186.4 | 191.9 | 3.0 | 12,4 |
Materials | 221.7 | 228.3 | 3.0 | 32,7 |
Heating installations | 210.0 | 218.0 | 3.8 | 45,5 |
Administrative expenses | 174.0 | 179.3 | 3.0 | 8,9 |
Labour cost1 | 186.4 | 191.9 | 3.0 | 13,4 |
Materials | 237.6 | 248.1 | 4.4 | 22,6 |
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12