July 2018 | July 2019 | Change from previous year (per cent) | Weight pr cent | |
---|---|---|---|---|
1Wage statistics for the 1st, 2nd, 3rd and 4th quarter are included in the construction cost of May, August, November and February respectively | ||||
Plumbing costs total | 214.1 | 220.5 | 3.0 | 100,0 |
Administrative expenses | 180.1 | 182.0 | 1.1 | 17,3 |
Labour costs1 | 191.9 | 194.9 | 1.6 | 26,0 |
Materials | 235.1 | 244.2 | 3.9 | 55,3 |
Sanitary installations | 213.2 | 217.5 | 2.0 | 54,5 |
Administrative expenses | 180.1 | 182.0 | 1.1 | 8,4 |
Labour cost1 | 191.9 | 194.9 | 1.6 | 12,4 |
Materials | 229.9 | 235.3 | 2.3 | 32,7 |
Heating installations | 215.4 | 224.0 | 4.0 | 45,5 |
Administrative expenses | 180.1 | 182.0 | 1.1 | 8,9 |
Labour cost1 | 191.9 | 194.9 | 1.6 | 13,4 |
Materials | 242.8 | 257.0 | 5.8 | 22,6 |
Find more figures
Find detailed figures from Construction cost index for plumbing works in office and commercial buildings
Contact
-
Hanne Beate Høiby
E-mail: hanne.hoiby@ssb.no
tel.: (+47) 40 81 14 28
-
Mona Takle
E-mail: mona.takle@ssb.no
tel.: (+47) 40 81 14 12